Present: William Dougherty, NI&S, chair and scribe; Richard Quintin-DBAA/ES; Steve Cox-CCS; Luke Sullivan-ITEE; Josh Aylor-NI&S; Mike Moyer-NI&S; Maynard Hoover-NI&S; Karen Herrington-Data Analytics; Laurie Zirkle-NI&S; Dave Hawes-SIS

Absent with regrets: Ken McCrery-TLOS


  • NI&S Facilities–Surge suppressors successfully installed. 
  • NI&S Data Center Management-All generators testing is needed; may shot for weekend before semester starts (Jan 20th, Sunday). Also time for UPS PM is due; battery changes and repairs are also in need.
  • NI&S DAS system update-AT&T will be on the air before spring semester; T-Mobile is also working on joining. 
  • DBAA/ES-Jan 13th, Sunday, WIndows based services will be impacted by updates; Financial Aid disbursements also this weekend; Jan 27th Banner upgrades due as well. ODA update not yet scheduled. 
  • Data Center network project issues are still occurring (BGP flaps), but vendor case is open. MLX hardware is out-of-service but will be phased out as soon as the Juniper issues. 
  • ARC Maintenance is underway so staff in NI&S DC program are pretty busy currently.