1.       May 13 -  EJBCA orientation with IMS, PP presentation and demo.

2.       June 23 -  Completion of VTCA CP and CPS policy document updates by PMA work group.

3.       June 30 - EJBCA testing feedback from IMS.

4.       July 2 - EJBCA orientation with 4HELP, PP presentation and demo.

5.       July 7 -  Review of VTCA CP and CPS document updates by PMA.

6.       July 9 -  Email notification to  Tech Support List and VTCA subscribers (cert exp July & Aug)

7.       July  17 - July 20 VTCA down for prod EJBCA implementation and PKI Website update.

8.       July 21 - VTCA running EJBCA - eProv will submit test CSRs for IMS to test.

9.       July 24 - EOL on LunaCA3 HSM.

10.     Aug 3 -  Aug 17 -  VTCA LunaSA 2U upgrade to LunaSA 1U.

11.     Sept  1 - Return VTCA LunaSA 2U HSMs to SafeNet - deadline Oct  1.

12.     Oct 30  - EOL on LunaSA 2U HSM.