IT Project Management for the Self-Service Password Reset Project
Invitees (* indicates unable to attend):
Attendees:
- Joyce Landreth *
- Daniel Fisher
- Karen Herrington
- Dean Kirstein
- Brad Tilley *
- Ken McCrery *
- Rhonda Randel
- Kevin Rooney
- Marc DeBonis *
- Mary Dunker *
- Randy Marchany *
- Wayne Donald *
Agenda
Note: This project follows the IT low risk project form.
- Project Time Management
- If requirements are complete (i.e., we have defined the scope of the project), then we need a list of tasks to accomplish the requirements, called define activities.
- I assume the activity list will come from Ken, Daniel, and Kevin???
- Ideally activities are narrow enough in scope (detailed enough) to be able to give a reasonable duration estimate.
- Next we organize activities in an order based on dependencies, called sequence activities.
- Next we estimate the type and quantity of resources required, called estimate activity resources.
- For this project that is primarily human resources costs.
- Next we estimate how long it will take to do each activity, called estimate activity durations.
- Once the activity durations are in place a network diagram is established that shows project work flow, dependencies, and the critical path.
- This is optional but is nice from a project management perspective.
- Finally, we develop [the] schedule so those doing the work know when their work is supposed to be done.
- Project Communications Management
- Review and complete the IT Project Communications Plan SSPWDReset-CommunicationsWorksheet.pdf
(blank form is here: https://secure.hosting.vt.edu/www.itplanning.org.vt.edu/pm/communicationsplan.html)
- Project Risk Management
- Review and complete the IT Project Risk Management Plan SSPWDReset-RiskWorksheet.pdf
(blank form is here: https://secure.hosting.vt.edu/www.itplanning.org.vt.edu/pm/riskplan.html)
- Review and complete the IT Project Security Plan SSPWDReset-SecurityForm.xls
(blank form is here: https://secure.hosting.vt.edu/www.itplanning.org.vt.edu/pm/securityplan.html)
- Project Quality Management
- Review and complete the IT Project Testing Plan SSPWDResetTestingWorksheet.pdf
(blank form is here: https://secure.hosting.vt.edu/www.itplanning.org.vt.edu/pm/testingplan.html)
- If needed, review and complete the IT Project Training Plan SSPWDReset-TrainingWorksheet.pdf
(blank form is here: https://secure.hosting.vt.edu/www.itplanning.org.vt.edu/pm/trainingplan.html)
- Project Human Resource Management
- Review and complete the IT Project Resources and Staffing Plan SSPWDReset-ResourcesStaffingWorksheet.pdf
(blank form is here: https://secure.hosting.vt.edu/www.itplanning.org.vt.edu/pm/resourcesstaffing.html)
- Other
- Production ownership, support, and maintenance