Team
Susan Brooker-Gross, Mary Dunker, Daniel Fisher, Karen Herrington, Kim Homer, Greg Kroll, Joyce Landreth, Randy Marchany, Kevin Rooney, Nate Smith, Brenda van Gelder
Agenda
- Continue requirements review with functional requirement #10
- Review Software Requirements Specification initial draft
- Review known project milestones and deadlines
Milestone |
Deadline |
Focus group meetings complete |
9/30/2010 |
Project scope and requirements documents complete |
11/1/2010 |
Internal Audit review of project scope and requirements documents |
12/15/2010 |
Self service PID password reset in production |
6/15/2011 |
Self service Banner/Oracle password reset in production |
10/1/2011 |
Self service Hokies password reset in production |
6/30/2012 |
- Begin discussion of known project issues and risks, mitigation and contingencies
Meeting Notes
- Continue requirements review...
- Discussed: "Discussion Questions" #7, 8, 9, & 10; "Functional Requirements" #10, 11, & 12.
- Review Software Requirements Specification initial draft
- Kevin asked that we read the requirements spec, especially the "User Classes and Cases (UC)" sub-section and let him know of any classes or cases he may have missed. Please post questions/comments/etc about the requirements spec to this wiki.
- Unless someone requests it, next week's meeting (10/19/2010) will likely be canceled.