Project Start Date: Mon 7/28/08
Project Finish Date: Sun 12/14/08
Resource Group |
Resource Name |
Task Name |
Duration |
Start |
Finish_Date |
Cost |
---|---|---|---|---|---|---|
|
|
Gather requirements |
30 days |
Mon 7/28/08 |
Fri 9/5/08 |
$0.00 |
|
|
Document requirements |
34 days |
Mon 7/28/08 |
Thu 9/11/08 |
$0.00 |
|
|
Design User Interface |
14 days |
Mon 9/8/08 |
Thu 9/25/08 |
$0.00 |
|
|
Design Web Service |
14 days |
Mon 9/8/08 |
Thu 9/25/08 |
$0.00 |
|
|
Develop User Interface |
14 days |
Thu 10/16/08 |
Tue 11/4/08 |
$0.00 |
|
|
Develop Web Service |
28 days |
Fri 9/26/08 |
Tue 11/4/08 |
$0.00 |
|
|
Perform Security Review |
1 day? |
Tue 11/4/08 |
Tue 11/4/08 |
$0.00 |
|
|
Approve PRPRD Deployment |
1 day? |
Tue 11/4/08 |
Tue 11/4/08 |
$0.00 |
|
|
Deploy to PRPRD |
1 day? |
Wed 11/5/08 |
Wed 11/5/08 |
$0.00 |
|
|
Write KB Articles |
7 days |
Fri 11/21/08 |
Fri 12/5/08 |
$0.00 |
|
|
Test |
20 days |
Thu 11/6/08 |
Mon 12/8/08 |
$0.00 |
|
|
Freeze PRPD Code |
7 days |
Tue 11/25/08 |
Mon 12/8/08 |
$0.00 |
|
|
Approve PROD Deployment |
1 day? |
Tue 12/9/08 |
Tue 12/9/08 |
$0.00 |
|
|
Publish KB Articles |
7 days |
Fri 12/5/08 |
Sun 12/14/08 |
$0.00 |
|
|
Deploy to PROD |
1 day? |
Sun 12/14/08 |
Sun 12/14/08 |
$0.00 |
Resource Group |
Resource Name |
Work |
Cost |
---|