Present: William Dougherty, NI&S, chair and scribe; Richard Quintin-DBAA/ES; Steve Cox-CCS; Luke Sullivan-ITEE;  Maynard Hoover-NI&S; Ken McCrery-TLOS; Laurie Zirkle-NI&S, Mike Moyer-NI&S DC; Richard Hach-NI&S. 


Data Center: 

Next week, (3/18-22/19) Batteries in B feed UPS will be changed (likely Thursday). Should be transparent to users/servers, but some repairs to capacitors and fans must also be done. This latter work needs a part to ship, so still needs to be scheduled (likely March 30th and 31st/Saturday & Sunday). UPS will be in bypass so some risk will exist. Two UPS (older ones; A and B feed) will be in scope. This will be done in sequence so only one UPS will be out of commission at a time. Systems should be configured to utilize more that a single UPS feed.